Validity test

Cases currently analysed:

  • base_oem: Base case off-grid OEM -> dispatch of same capacities doesn’t work out

  • oem_grid_tied_mg: OEM of grid-tied MG

  • interconnected_buy: Base OEM interconnected with MG, buy (fix PCC)

  • interconnected_buysell: Base OEM interconnected with MG, buy and sell (fix PCC)

  • sole_maingrid: Supply only by national grid (no stability criterion)

Costs

  • Distribution grid costs are included in all cases

  • Main grid interconnection costs are included in all cases with interconnection

  • Slight difference in PCC capacity (oem_grid_tied, sole_maingrid), as capacity not batch capacities are

base_oem

interconnected_buy

interconnected_sell

sole_maingrid

oem_grid_tied_mg